Deploy additional servers and infrastructure for fast models and slaves
LAVA is currently running on a single server in the validation farm. In order to support fast models, we will need to have systems dedicated to running the fast models software for a LAVA client. Additionally, having LAVA constrained to a single machine is causing some performance bottlenecks that we have observed. Remaining servers will be used as slaves to offload of of the more resource intensive tasks.
Blueprint information
- Status:
- Complete
- Approver:
- Paul Larson
- Priority:
- High
- Drafter:
- Dave Pigott
- Direction:
- Approved
- Assignee:
- Dave Pigott
- Definition:
- Approved
- Series goal:
- Accepted for trunk
- Implementation:
-
Implemented
- Milestone target:
-
2012.01
- Started by
- Fathi Boudra
- Completed by
- Fathi Boudra
Related branches
Related bugs
Sprints
Whiteboard
[pwlars 2011-12-14] The servers have been ordered I believe, but have not yet arrived. Blocked on this obviously until they actually get here, but I'm not expecting that to happen by tomorrow's release
[fboudra, 2011-16-12] re-target to 2012.01.
[asac, Jan 6, 2011] please comment on blocked state every other day if something doesn't move. e.g. blueprint reader wants to understand the problem blocking install/configure work item.
[pwlars 2012-01-06] previously blocked because the servers were not in, so this couldn't continue until they arrived. It's likely that they arrived over the holidays but Dave isn't back until next week to continue this. Will try to get confirmation from someone else in the office about the status of the order.
[pwlars 2012-01-10] Unblocked - servers have arrived and are in the process of being setup.
[pwlars 2012-01-30] Servers are installed, one has the fast models software installed, a decision was made to pursue setting the others up in a cloud for flexible deployment
[fboudra, 2012-02-01] rabbitmq setup is blocked until the cloud has been set up, which is blocked until the new e-net switch arrives. Move the WI to Celery blueprint.
Meta:
Headline: 5 new servers to take the load off v.l.o
Acceptance: New servers available and in use
Roadmap id: LAVA2011-
Work Items
Work items:
Source and purchase new servers: DONE
Rack and cable new servers: DONE
install OS on new servers: DONE
install fast model software on servers to be used for fast models clients: DONE